MAKE OPINIONS VISIBLE.
English

After the PI Planning confidence vote: improve the plan

The vote is complete and some scores are low. Now the facilitation work begins. This guide helps RTEs and planning teams turn the distribution into concrete changes instead of simply working toward a better average.

Sign in with your facil4 account to create a poll. Participants do not need an account.

First check: did everyone assess the same plan?

Ask which plan version and objectives informed the vote. During Big Room Planning, changes to one team’s plan can reach other teams late. Low confidence may indicate missing information or an unresolved problem. Do not assume either explanation too quickly.

Display the current version and summarize key changes to scope and PI Objectives. Remote participants need the same information as people in the room.

Collect concerns without revealing votes

Ask the whole group: “Which condition is still missing?” Invite specific observations instead of names or justifications. Offer written follow-up through a suitable existing channel if someone does not want to speak to the group. This facil4 vote does not collect free-text comments.

Group topics for discussion: capacity, dependencies, unclear requirements and technical risks. These categories help you work through concerns; they cannot be inferred from a numerical score.

Work through cross-team dependencies concretely

For example, Team A plans an integration in week two, while Team B cannot supply the interface until week four. “Coordinate better” does not resolve that. Explore an earlier small slice, a different sequence or reduced scope.

Have the affected teams confirm the new agreement. Record what will be delivered, who owns it and when you will review the assumption. Use your existing planning tool for this.

When another vote is useful

Vote again when something relevant in the assessed plan changes or a major uncertainty has been clarified. Explain the changes before the new vote. In facil4, create a new poll using the same template; previous votes remain stored.

Confidence may still be low. Decide deliberately whether to reduce scope, investigate further or carry an uncertainty with clear ownership. Another vote alone does not address a risk.

Close the loop remotely and in hybrid groups

Share the agreements as well as the result screen. Read out the main points and explicitly leave room for remote participants to ask questions. Record unresolved topics, owners and a review date.

As planning continues, this list matters more than the final average. The linked template contains the question, scale and direct entry for your next PI Planning confidence vote.

Ready for your vote?

Open the template in the cockpit, sign in and review the question. Create and start the vote before sharing the link or QR code.

Start a PI Planning confidence vote

Explore next